Invoice

From:

1-13819 232nd Street
Maple RIdge, BC, V4R0C7
Ph: 778-833-3473

info@cands.ca

Invoice Number INV-0002
Invoice Date February 25, 2020
Total Due $6,284.25
To:
Adastra Labs

5451 275 Street Langley

EXTRACTOR

CONNECT GLYCOL, CO2, EXHAUST AND AIR LINES TO EXTRACTOR MACHINE. FULLY INSULATE LINES AND CONNECT FROM STORAGE UNITS IN MECHANICAL ROOM TO MACHINE ITSELF. CREATE CEILING PANEL CONNECTIONS TO PROVIDE STREAMLINE APPEARANCE AS DISCUSSED. TEST CO2 LINES AND AIR LINES TO 90PSI AND ALL HOLDING PRESSURE.

AIR COMPRESSOR

BUILD AND INSTALL AIR COMPRESSOR MANIFOLD. CONNECT AIR LINES AND ALL ASSOCIATED COPPER. INSTALL NEW CONDENSATE DRAIN LINE INTO MECHANICAL ROOM. TEST RUN AND PRESSURE TEST DISTRIBUTION SYSTEM THROUGHOUT SPACE. ALL HOLDING 80psi AIR.

Hrs/Qty Service Rate/PriceAdjustSub Total
1 EXTRACTOR MACHINE CONNECTIONS

GLYCOL
SWAGELOK CO2
SWAGELOCK EXHAUST
ARMAFLEX INSULATION
ALL CONNECTIONS FOR CEILING TILE MANIFOLD
PRESSURE RELIEF VALVES
TESTED AND HOLDING PRESSURE

$4,320.000.00%$4,320.00
1 AIR COMPRESSOR PIPING AND CONNECTIONS. MANIFOLD AND PIPING TO AIR LINE ROUGH IN MAINLAND PLUMBING INSTALLED. ALL PIPING FITTINGS CONNECTIONS AND HOSES INCLUDED

PIPING AND CONNECTIONS. MANIFOLD AND PIPING TO AIR LINE ROUGH IN MAINLAND PLUMBING INSTALLED. ALL PIPING FITTINGS CONNECTIONS AND HOSES INCLUDED
TESTED AND HOLDING PRESSURE
CONNECTOR FITTINGS PROVIDED FOR ALL AIR SERVICE PORTS IN SPACE

$1,665.000.00%$1,665.00
Sub Total $5,985.00
GST $299.25