Project: Golden Ears Building 800 Upgrade
Project Address: 19055 Airport Way
Project Scope:
- Supply and installation of (1) Lot LV Siemens Distribution
- Unit Substation Modifications
- Supply and installation of quad logic metering
- Supply and installation of LV metering
- Supply and installation of HV cabling
- Termination of HV cabling
- Removal and replacement of existing 1400A and 1600A breakers with 3000A Lug Pad
- Commissioning and Ground Testing
- Testing of HV cabling
- Co ordination Study for 3000kVA and 2000kVA unit subs
- Insulations Tests
- Resistance Tests
- Equipment Inspection
- Underground Duct Work
- Replacement of 70A breakers in existing switchgear
- Re routing of existing feeder cables to existing switchgear to be fed from new switchgear
- Crane lift for 3000kva sub
- Crane lift for 2000kva sub
Exclusions:
- Civil Work
- Cutting
- Coring
- All items downstream of new switchgear not including existing switchgear
- Bollards by others
- Concrete pads by others
- Pullboxes
Notes:
- Given the complexity of the project shutdown times, all parties are to come to an agreement of shutdown procedures and project progress co ordination.
- If backup generators are to be added to the project scope, these items will need to be discussed and agreed upon at additional cost to the project.
- Any items not listed within project scope are in additional cost to this quotation.